Costs Budgeting: Are Incurred Costs Untouchable? - Ian Miller, 1 Chancery Lane

20/09/15. How do you get around costs budgeting? One might have thought by incurring considerable costs before the CCMC: Practice direction 3E 7.4 states that the court may not approve costs incurred before the date of a budget. In CIP Properties Ltd v Galliford Try Infrastructure [2015] EWHC 481 Coulson J came up with an order which would prevent parties to litigation trying to get around the process. In the recent case of GSK Project Management Ltd v QPR Holdings Limited [2015] EWHC 2274 Stuart-Smith J made a similar order (will it become known as a ‘Coulson Order’ or a ‘CIP Order?)
In GSK Stuart-Smith J was managing the costs in a dispute over works carried out at Queens Park Rangers’ Loftus Road ground. The claim was essentially for £805,675 of unpaid sums due under the contract and there was a counterclaim for defective works.
The claimant’s costs budget was for £824,038 and it stated that over £310,000 had been incurred already. The budget therefore exceeded the sums at stake. The defendant’s budget was £455,554 in total although, as the judge commented, a comparison was not appropriate because...
Image ©iStockphoto.com/imagestock